July 20, 2008
see more
July 18, 2008
see more
July 16, 2008
see more
July 14, 2008
see more
July 11, 2008
see more
July 7, 2008
see more
July 4, 2008
see more
July 2, 2008
see more
After 10 days of soaking rain Vasco was finally able to start laying the base down. Assuming the weather cooperates they should finish up next week. Field Turf is scheduled to be delivered on July 10th and begin laying the carpet the week of July 14th. Once again depending on the weather it will take them 3-4 weeks to complete the work.
June 28, 2008
see more
June 25, 2008
see more
June 20, 2008
see more
June 19, 2008
see more
June 18, 2008
see more
June 13, 2008
see more
May 30, 2008
see more
May 29, 2008
see more
May 28, 2008
see more
May 20, 2008
see more
May 19, 2008 --- Day 1
see more
May 19, 2008 --- Ground Breaking -